The construction of the terminal building at Surat Airport is close to completion, at an expenditure of 138.48 crores. Simultaneously, progress is being made on the parallel taxi track, which is being constructed at a cost of 63.13 crores, and the construction of an adjacent canopy to the terminal building, costing 15.57 crores, is also underway. These developments will significantly enhance the facilities at Surat Airport.
Additionally, the apron extension and parallel taxi track work are reported to have been 72 percent complete, according to Surat Airport Authority. Once the upgrades are finalized, the terminal building will accommodate up to 1800 passengers during peak hours, boasting five aerobridges, five baggage carousels, and ample passenger space with various amenities.
Author-City Features